Saturday, May 31, 2008

Yes, the Carpentary has arrived!

The carpenter have been doing up all the works and it is half done now... Consider quite fast coz itz oni 1 day work!
The area behind the main wooden door (we did this carpentary to cover up the circuit breaker box and the racks installed inside can be used as a key press or to hang some umbrellas. Still awaiting mirror...):

Home Shelther (Almost done too, except awaiting mirror and some part of carpentary still not up yet):

Kitchen Cabinet (Awiting granite top, hood and hob and the sink tap. The blum system still havent installed yet):



Common Toilet vanity cabinet:
Masterbedroom seatee (A request to my ID that i need drawers so as to put my towel, bedsheet etc in due to the small wardrobe we have in the masterbedroom. The extreme right side are slots used to put dvd player and maybe the scv box):
Masterbedroom 2 side tables:

Masterbedroom Wardrobe (Very small due to space constraint):

Masterbedroom Toilet Vanity Cupboard (With 2 sliding door and 2 drawers):

Will post more pics soon after the capentary is done! Hope to move in by 15june... =)

Sofa bought!

Bought this set of sofa from Natural Living @ Park Mall!


and get this cushion free! (The sales person gave me 3, and i planned to put it at the master bedroom seatee)


Friday, May 30, 2008

Shopping Time! (bought the pendant lights)

Yesterday night we went to shop for the pendant lights and it will be installed on 7 june... Went to the whole stretch of Jalan Besar and Balestier.... Found that the cheapest area is Jalan Besar!

These are the pendant lights we bought!
The foyer lights! But we are only getting 1 instead of 5... 1 small 1 should b enough for the foyer light:

The Dining Table light!

This is the 1 we love MOST! Crystal pendant light for our Master bedroom!

We went to many many many shops and finally got the right set of sofa we wanted! This is the set of 3-seater sofa we are going to buy tonight!

Will be uploading the status of the caroentary work soon!

Monday, May 19, 2008

Lacquer for pebbles and mosaic tiles...

When for a run this morning with hubby @ bedok reservoir and then when up to our unit to take a peep! The reno work have been veri quiet recently because not much work need to be done and the only thing left is the mirror work and carpentary! Our resort home have plenty of woody thing so the big milestone is coming! Should b ard 30th May then the carpentary will arrive. Hehe...
Meanwhile, here are the shots for our lacquered pebble n mosaic tiles...

The Masterbedroom Toilet:

The common Toilet:


Bedroom 3:

The Foyer:

Saturday, May 17, 2008

Acid Wash Done! Awaiting Carpentary...

Finally our home is having sparkles and itz pretty clean after the acid wash. Now a clearer and cleaner view of our home on 15th May 2008... The paper protection for the floor have been removed!

The Foyer:

Living Room:
Bedroom 3:


Service Yard:




Kitchen:



Bedroom 2:


Common Toilet:




Masterbedroom:

Masterbedroom toilet:

Saturday, May 10, 2008

Aircon unit up... Finally!

The aircon man came to install the air con unit tis afternn. Can say their workmanship not realli gd. Veri rough... And veri scared they knock against my glass doors! Keep looking at how they work. Haiz. Lucky they nv scratch my nice nice aircon unit... Here's all my Mitsubitshi electric system 4:

The compressor at the air con ledge:

MBR aircon unit:

Bedroom 2 aircon unit:
Bedroom 3 aircon unit:

The big aircon unit at dining area... Muz eat cold dish like sushi liaoz! haha!

Friday, May 9, 2008

Glass Work and Toilet Bowls installed...

1 major milestone... Glasswork juz installed!

MBR toilet glass door (shower screen not up yet):


Bedroom 3 glass fixed wall + sliding door (gng 2 ask Lisa to do a box-up):


Kitchen Sliding Door (From the inside): Ask the tiler to put in some homogeneous steps at the foyer:Toilet bowls and heater and rain shower installed! Here's the preview:

The Ariston 25L Water heater @ Common toilet:

Common Toilet Bowl:
MBR white toilet bowl! TOTO brand + expensive!!!:

Rain shower @ MBR toilet:

we were to inspect the lighting installation and they were nicely done by the contractor. However, there is a few hiccups such that they install the wrong lighting colour. (eg. warm light n white light) Oni 2 of them is affected and i ask Lisa to get it changed for me. So i told her b4 some other lighting colours got confused. From the pictures below, u can c that my lights model are more or less the same. Hehe.

Dining Area Light (Still have a pendant light not fixed yet):
Living Room Lights (Still have veneer beam lights not fixed yet): Service yard light: Kitchen Light:
Common Toilet Light:

Bedroom 2 light:

Bedroom 3 light:

Masterbedroom toilet lighting:
Masterbedroom wardrobe area lighting:
The aircon man did come and fix the aircon yesterday, n last min say he sick at abt 1pm. The installation was supposed to be at 3pm. So, a penalty of doubt, we arrange for him to install on next mon. He agreed and after another hour, he call backed agn and ask if he could install 2moro. Veri troublesome... Haiz. So in the end have to meet him 3pm 2dae agan...
More pictures to be updated!